Palmerston Hospital Update

  • May 19, 2016

Palmerston Hospital Update

The works carried out this week includes: Tie reo bar to stair and lift shaft walls; Close off form work to stair and lift shaft walls; Pour stair and lift shaft walls up to level one; Under slab sewer drains; Lay fire and potable water services; Lay main sewer drain; Lay stormwater drains; Pad footings poured to date is 277; Columns poured to date 272; Temp power supply to site; Pour ground slab to building four (Ambulatory Care Ward); Installation of site amenities; Start formwork for building one, second floor slab; and Scaffold erection around building one.